|
||||||||||||||
|
Latest News |
Delay in building nuclear fuel
storage blamed on foreign firms
ISAR-TASS
January 31, 2007
(For personal use only)
Chiefs of the Russian and Ukrainian supervisory organizations
are equally critical of the way the project for the construction of a storage
for spent nuclear fuel in the Chernobyl exclusion zone, financed by the European
Union, is being implemented. This is seen from the press release transmitted to
Itar-Tass following the talks in Kiev between the head of the Federal Service
for Environmental, Technological and Nuclear Supervision, Konstantin Pulikovsky,
and the head of Ukraine’s State Committee for Nuclear Regulation, Yelena
Mikolaichuk.
The delay in the construction of the second section of the spent nuclear fuel
storage in the territory of the Chernobyl nuclear power plant were discussed,
among other things, says the document. Pulikovsky believes there should be no
other such construction project, either in Ukraine or in Russia. “This is
another example showing that not everything foreign companies offer should be
taken at face value,” he said. Meanwhile, “both Russia and Ukraine have
technologies and highly qualified specialists to implement such projects on
their own,” Pulikovsky said.
Mikolaichuk, in her turn, said that Ukraine would make no more such errors, as
with the construction of the storage at the Chernobyl nuclear power plant.
Ukraine’s State Committee for Nuclear Regulation tightened control over
contactor organizations working in nuclear energy, also at the stage of choosing
the contractor. During the negotiations, Mikolaichuk said most contracts with
foreign companies in that area had failed. She said the contracts had not been
fulfilled as foreign partners do not keep the schedule and raise the costs of
their services. The storage for spent nuclear fuel should have gone into
operation in 2003, then its opening was postponed to 2005, and it has not yet
gone into operation. We are faced with the problem of changing the project,
overhauling it, she said.
Pulikovsky remarked that Russia, too, had similar bitter experience, Sakhalin-2
project. The foreign companies participating in the project started rapidly
increasing expenditures for its implementation.
Ukraine’s Minister for Emergency Situations Nestor Shufrich said the other day
only fuel from reactors of the Chernobyl plant would be contained in the
storages being built on the territory of the Chernobyl nuclear power plant. He
said the construction of the storage is financed by the Donor Assembly of the
Nuclear Safety Account with the participation of the European Bank for
Reconstruction and Development (EBRD) that provides funds for the programmes to
clear the after-effects of the Chernobyl disaster. Ukraine’s State Committee for
Nuclear Regulation reported last year that the storage for spent nuclear fuel at
Chernobyl would be put to use not earlier than in 2010. It is the French
contractor, Framatome consortium, and the designer, the US Holtee lnt., that are
to blame for this delay.